Replacing a panel, upgrading to 200 amps, adding a generator or a new circuit? Most of that work needs an electrical permit. Which office issues it depends on your address. Here is how it works in the City of Pensacola and unincorporated Escambia County, what the City’s published fees are, and where to check the official sources.

Important: this is a plain-English summary of public City and County pages, checked on October 19, 2026. It isn’t legal advice, and fees and rules change. The permitting office sets the final fee when the application is processed, so confirm with the office (or your electrician) before you rely on a number.

Which office issues your permit?

Where the home is Who issues electrical permits
Inside Pensacola city limits City of Pensacola Building Inspections, 5th floor of City Hall, 222 W. Main St. (850-436-5600)
Unincorporated Escambia County (for example Cantonment, Ferry Pass, Myrtle Grove, Warrington, Perdido Key) Escambia County Building Services, 3363 West Park Place (850-595-3550)
Gulf Breeze, Pace, Milton, Navarre Santa Rosa County or the city where applicable. Not covered on this page.

A Pensacola mailing address doesn’t always mean city limits. If you aren’t sure, check your property record or ask the office before work starts.

What electrical work needs a permit?

Escambia County’s permitting page lists two electrical permit types for homes:

  • Electrical, basic work: changing or adding to existing circuits, adding loads to the panel, and wiring new equipment or appliances.
  • Electrical service change: changing a panel from fuses to circuit breakers, or upgrading to a larger rating (for example 100 to 200 amps).

In practice that covers most of what homeowners ask about: panel replacements and service upgrades, standby generators and transfer switches, EV charger circuits and new dedicated circuits. The City of Pensacola also has an Electrical Generator ATS Affidavit form and a “Rewiring Requires Certain Conditions” guideline on its Electrical Information page. Swapping a light fixture or a like-for-like outlet is usually treated differently, so ask the office if you’re unsure.

City of Pensacola electrical permit fees (2026)

These figures come from the City’s Simplified Fee Schedule for residential alterations and Chapter 7-14 of the City Code (fees). They apply only inside city limits.

Fee Amount (City published schedule)
Administrative application fee (every permit) $40
Electrical service, 0 to 100 amps $90
Electrical service, 101 to 200 amps $95
Electrical service, 201 to 400 amps $125
Electrical service, 401 to 600 amps $175
Inspection (minimum fee, per inspection) $50
Temporary or construction pole service $50
Swimming pools, spas and hot tubs $100
Residential fire and security systems $50
DCA surcharge 1% of permit, review and inspection fees (rounded up)
DBPR surcharge 1.5% of permit, review and inspection fees (rounded up)
Paying by credit card 3% service charge
Starting work before the permit (first time) 4 times the permit fee

The service fee covers residential and commercial services, including generators and service changes, per City Code Sec. 7-14-2(b).

Worked example: 200-amp panel replacement inside city limits

Using the published schedule, a 200-amp service change with one $50 inspection would add up roughly like this: $40 application + $95 service + $50 inspection = $185, plus a $2 DCA surcharge and a $3 DBPR surcharge, for about $190. More inspections add $50 each, and a card payment adds 3%. This is an illustrative estimate from the schedule, not a quote. The City calculates the actual fee.

The permit fee is a small part of the job. For the work itself, see typical ranges in our Pensacola electrical cost guide. In most quotes the electrician pulls the permit and includes the fee, so ask whether it’s included.

Escambia County electrical permit fees

Escambia County Building Services doesn’t post a simple residential electrical fee table on its permitting pages. Instead it offers an Electrical Permit Fee Estimate form: you fill in the service size, building type, type of work and construction cost, and fax it to 850-595-3589 for an estimate. The form states that the final fee is set when the permit application is complete, and that fees charged by other agencies aren’t included.

Other County rules worth knowing:

  • Notarized application. A completed application needs the notarized signature of the contractor applying. The County can provide a notary when a technician is available.
  • Notice of Commencement. A recorded Notice of Commencement is required for work costing $5,000 or more (HVAC changeouts at $15,000 and above), with a certified copy provided.
  • Online access. The County links to MyGovernmentOnline for contractor and citizen permit access.

How the permit process works

  1. Confirm the office. City limits or unincorporated county (see the table above).
  2. Apply. City of Pensacola permits are handled through the MGO (MyGovernmentOnline) portal. Paper applications are only needed if you aren’t applying online. Electrical sub-permits tied to a larger project are submitted online as an “Add-to-Existing” permit.
  3. Pay the fees and wait for the permit to be issued before work starts. In the City, starting early can cost 4 times the permit fee.
  4. Schedule inspections. In the City, inspections are booked online in MGO or by phone through the IVR line at (866) 957-3764, option 5.
  5. Coordinate with the utility. Service changes and meter work also need the power company. Your electrician usually handles this.
  6. Final inspection closes the permit. Keep the record for insurance and resale.

Codes and permit timelines in the City (2026)

  • The City currently enforces the 2023 Florida Building Code (8th edition) and the 2020 National Electrical Code (NFPA 70). Projects submitted on or after December 31, 2026 must meet the 2026 Florida Building Code.
  • Residential permits issued on or after July 1, 2026 are valid for one year, or until the start of a new code cycle if that is longer. Permits issued earlier are valid for 180 days. Extension and renewal requests are uploaded in MGO and cost a fee.
  • Since May 1, 2026, all new construction in the City needs an early power release inspection, with the fee assessed on the electrical permit.

Can a homeowner pull the permit?

Florida has an owner-builder exemption that can let homeowners permit some work on their own home, with conditions. Electrical work carries real fire and shock risk, and the permitting office decides whether you qualify. Ask the City or County directly before you plan around it. For most panel, service and generator work, a Florida-licensed electrical contractor pulls the permit. We don’t verify licenses, so check any electrician’s license at myfloridalicense.com before hiring.

Frequently asked questions

How much is a 200-amp electrical permit in Pensacola?
Inside city limits, the City’s published schedule lists a $40 application fee and $95 for a 101 to 200 amp service, plus $50 per inspection and small state surcharges. One inspection works out to roughly $190. The City sets the final fee.
Does Escambia County publish electrical permit fees?
The County offers an Electrical Permit Fee Estimate form that you fax in for an estimate. The final fee is set when the permit application is complete.
What happens if work starts without a permit?
In the City of Pensacola, a first offense is charged 4 times the permit fee, and repeat offenses can be prosecuted as code violations. Unpermitted work can also cause problems with insurance and when you sell.
Who usually pulls the electrical permit?
Usually the electrical contractor doing the work, who includes the fee in the quote. Ask whether the permit is included when you compare quotes.